Following more screwups by tradies last week that put things in jeopardy again, it took some pushing and shoving to get the SS to agree to having the council inspection on Monday. Thankfully, it did happen, and passed.
Some wisdom we've gleaned about these final stages of the build, all of you whom have reached this stage will no doubt relate to:
- Expect that nothing you've been promised will actually take place, then you might be pleasantly surprised on some rare occasions. But you all know that already. :)
- Organise bank settlement request (and valuation inspection) early. In our case it was almost 10 days between submitting the final invoice and being able to collect the final cheque.
- Do not expect the same expediency of the builder's admin and accounts departments in issuing the aforementioned final paperwork as they do with issuing the progress payment invoices.
- Don't expect the builder's QA processes to be adequate.
- Don't expect that an independent inspection will catch everything either.
- Don't expect that the builder will agree to fix everything, there will inevitably be some compromises.
- Do organise telco and pay-TV connections well in advance.
- Expect to have "fun" trying to guess the handover day (officially, we had TWO days notice) and keep flooring/blinds/landscaping/furniture companies on "hot standby".
- Do expect that eventually The Day will arrive and you won't believe it's finally here either.
Stay tuned...