Hello buildees,
Same as all of you who are at these final stages, we're getting served numerous promises - virtually none of them delivered - and a whole lot of nada happening on site.
After an uneventful week last week, at the start of this week we were assured that the following would take place:
- Door handles installed
- Garage door installed (has been promised for a couple of weeks now)
- Safety fences down
- Site clean
- Perimeter pest control installed
- Interior builder's clean
- Aluminium angle brackets installed above window reveals to cover gaps
- Render patched and painted - front portico and rear outdoor room posts
- Cupboard shelving and doors installed
- Shower screens and mirrors installed
- Downpipe connections
As of this morning, only the first item on the list has been done.
Our SS remains evasive on a PCI date. Apparently one of the major hold-ups is that the showers screen / mirror / cupboard shelving company (beginning with "St") is inundated with work due to the flurry of houses being completed as a result of the <$600k stamp duty exemption which came in on July 1 last year. Did these companies, especially the builders - not see this coming? Given that we have been unconditionally locked-in to our cupboard/shower screen choices for more than 9 months, why were these orders not scheduled for delivery earlier to compensate for the slow lead times?
How are you all going with your promises?